List of Non National Road Contracts 2011
Map and details of Current Road Contracts
N56 Kilraine to Glenties Pavement Strengthening Contract 2011 (COMPLETED)
This project comprises the overlaying of the N56 National Secondary Route for an approximate length of 2.0km. The major elements of the work include establishment, maintenance and removal of traffic management for the works, AC regulation, AC binder course and Clause 942 wearing course to stated tolerances, drainage, road markings, road studs and collation of information for inclusion in the safety file for the project.
Site Location Map
Proposed Construction Period:
Thursday 24th November 2011 - Friday 23rd December 2011
Traffic Management Arrangements:
Delays can be expected.
Traffic lights and/or stop/go system in place.
-----------------------------------------------------------------------------------------------------------------------------------
N13 Manor to Newtown Pavement Strengthening Contract 2011 (Phase 1 & 2) (COMPLETED)
This contract involves overlaying the existing pavement on two separate sections of the N13 National Primary Route, (Phase 1) is 1.64Km in length and (Phase 2) is 1.66Km in length. The major elements of work include establishment, maintenance and removal of traffic management for the works, laying of Bituminous Regulating Material and Binder Course to achieve tolerances appropriate for Hot Rolled Asphalt Surface Course to a depth of 45mm, road lining, drainage, safety barrier and collation of information for inclusion in the safety file for the project.
Location Map - Phase 1
Location Map - Phase 2
-----------------------------------------------------------------------------------------------------------------------------------
N15 Ardinawark to Cashelnavean Pavement Strengthening Contract 2011 (COMPLETED)
The project will involve the overlaying of the existing pavement of a 6.1km section on the N15 National Primary Road located between Donegal Town and Ballybofey. The main elements of work include acceptance of PSCS, regulating and surfacing the existing carriageway, installation of safety barrier, road studs, road lining and accommodation works.
Proposed Construction Period:
October 2011 - January 2012
Traffic Management Arrangements:
Delays can be expected at Barnesmore Gap on the N15 between
Donegal Town and Ballybofey until 2nd December 2011.
Traffic lights and/or stop/go system in place.
Site Location Map
-----------------------------------------------------------------------------------------------------------------------------------
N56 Tirlin to Drumnaraw 2011
This project comprises the overlaying of the N56 National Secondary Route for an approximate length of 1.5km. The major elements of the work include establishment, maintenance and removal of traffic management for the works, AC Regulation, AC Binder Course and Clause 942 to stated tolerance, earthworks, installation of watermain and two culverts, ducting, drainage, road markings, safety barrier and collation of information for inclusion in the safety file for the project.
Proposed Construction Period:
October 2011 - March 2012
Traffic Management Arrangements
Delays can be expected at the townlands of Tirlin and
Drumnaraw on the N56 between Termon and Creeslough until
23rd December 2011. Traffic lights in place. Diversions may be
required.
Site Location Map
-----------------------------------------------------------------------------------------------------------------------------------
N13 Lurgybrack Pavement Strengthening Contract 2011 (COMPLETED)
This project involves overlaying the existing pavement on a section of the N13 National Primary Route 1.1Km in length. The major elements of work include establishment, maintenance and removal of traffic management for the works, Regulation, Binder Course to achieve tolerances appropriate for Hot Rolled Asphalt Surface Course to a depth of 45mm, road lining, drainage and collation of information for inclusion in the safety file for the project
Proposed Construction Period:
October 2011 - December 2011
Traffic Management Arrangements
Delays can be expected. Traffic Management in operation until 06th December 2011.
.
Site Location Map
-----------------------------------------------------------------------------------------------------------------------------------
N13 Drumkeen to Treantaboy Pavement Strengthening Contract 2011 (COMPLETED)
This project involves overlaying the existing pavement on a section of the N13 National Primary Route. The major elements of work include establishment, maintenance and removal of traffic management for the works, Regulation, Binder Course to achieve tolerances appropriate for Hot Rolled Asphalt Surface Course to a depth of 45mm, road lining, drainage and collation of information for inclusion in the safety file for the project.
Proposed Construction Period:
October 2011 - December 2011
Traffic Management Arrangements
Delays can be expected on the N13 between Stranorlar and
Letterkenny until 18th November 2011. Traffic lights and/or
stop/go system in place.
.
Site Location Map
-----------------------------------------------------------------------------------------------------------------------------------
Please click link below for traffic information in relation to all schemes highlighted above:
http://www.aaireland.ie/AA/AA-Roadwatch.aspx
-----------------------------------------------------------------------------------------------------------------------------------
N15 Improvement Contract 2011 -Lifford to Haw (Curraghalane to Unshinagh Lower) (COMPLETED)
This contract involves overlaying the existing pavement on the N15 National Primary Route. The scheme is approximately 1.38km in length. The major elements of the work include establishment, maintainence and removal of traffic management for the works, laying of Bituminous Regulating Material and Binder Course to achieve tolerances appropriate for Hot Rolled Asphalt Surface Course to a depth of 45mm, road lining, drainage and collation of information for inclusion in the safety file for the project.
Site Location Map
Proposed Construction Period
28th November 2011 - 23rd December 2011
Traffic Management Arrangements
Delays can be expected on the N15 Lifford to Stranorlar road between the townlands of Curraghalane to Unshinagh Lower until 23rd December 2011. Traffic lights and/or
stop/go system in place.
-----------------------------------------------------------------------------------------------------------------------------------
N56 Falcarragh to Gortahork Pavement Strengthening Contract 2011
This project involves overlaying the existing pavement on a section of the N56 National Secondary Route 2.7km in length. The major elements of work include establishment, maintenance and removal of traffic management for the works, regulation, binder course to achieve tolerances appropriate for Clause 942 Surface Course to a depth of 40mm, road lining, drainage, safety barrier and collation of information for inclusion in the safety file for the project
Site Location Map
Proposed Construction Period
1st December 2011 - 29th February 2012
Traffic Management Arrangements
Delays can be expected on the N56 Falcarragh to Gortahork PSC 2011 from 1st December 2011 until 29th February 2012. Traffic lights, Convoy system and/or
stop/go system will be in place.