Please note the Traffic Management update from now until Friday 24th September. If there are any particular concerns with the running of the Traffic Management Donegal County Council should be contacted at 074 91 53900 during working hours.
Out of hours emergency call Donegal County Council at 074 91 72288 or Ballybofey Garda Station at 074 91 37740.
Road works at Lidl to Topaz Filling Station
Work will continue on this section between TSA and Topaz Filling Station, and one-way STOP/GO will be in operation during working hours. Traffic lights will be in operation in the evening/overnight and at the weekend.
Day |
Date |
Implemented Traffic Management |
Friday |
14/09/2018 |
One Way STOP / GO |
Saturday |
15/09/2018 |
Open Two Way Traffic |
Sunday |
16/09/2018 |
Open Two Way Traffic |
Monday |
17/09/2018 |
One Way STOP / GO |
Tuesday |
18/09/2018 |
One Way STOP / GO |
Wednesday |
19/09/2018 |
One Way STOP / GO |
Thursday |
20/09/2018 |
One Way STOP / GO |
Friday |
21/09/2018 |
One Way STOP / GO |
Saturday |
22/09/2018 |
One Way Traffic Lights |
Sunday |
23/09/2018 |
One Way Traffic Lights |
Monday |
24/09/2018 |
One Way STOP / GO |
Road Works at Cappry
Works will carry on throughout the period from Monday to Friday. One-way TRAFFIC LIGHTS will be in operation on these days during working hours.
Blackburn Bridge to Cappry |
||
Day |
Date |
Implemented Traffic Management |
Friday |
14/09/2018 |
One Way STOP / GO |
Saturday |
15/09/2018 |
Open Two Way Traffic |
Sunday |
16/09/2018 |
Open Two Way Traffic |
Monday |
17/09/2018 |
One Traffic Lights (working hours) |
Tuesday |
18/09/2018 |
One Traffic Lights (working hours) |
Wednesday |
19/09/2018 |
One Traffic Lights (working hours) |
Thursday |
20/09/2018 |
One Traffic Lights (working hours) |
Friday |
21/09/2018 |
One Traffic Lights (working hours) |
Saturday |
22/09/2018 |
Open Two Way Traffic |
Sunday |
23/09/2018 |
Open Two Way Traffic |
Monday |
24/09/2018 |
One Traffic Lights (working hours) |
Works at the Finn Bridge
Two-way traffic is to be maintained throughout the period during peak hours. Single lane closures can be implemented after 18:30 and before 08:30.
FinnBridge |
||
Day |
Date |
Implemented Traffic Management |
Friday |
14/09/2018 |
Open Two Way Traffic |
Saturday |
15/09/2018 |
Open Two Way Traffic |
Sunday |
16/09/2018 |
Open Two Way Traffic |
Monday |
17/09/2018 |
Open Two Way Traffic (during day) One way (outside peak hours) |
Tuesday |
18/09/2018 |
Open Two Way Traffic (during day) One way (outside peak hours) |
Wednesday |
19/09/2018 |
Open Two Way Traffic (during day) One way (outside peak hours) |
Thursday |
20/09/2018 |
Open Two Way Traffic (during day) One way (outside peak hours) |
Friday |
21/09/2018 |
Open Two Way Traffic (during day) One way (outside peak hours) |
Saturday |
22/09/2018 |
Open Two Way Traffic |
Sunday |
23/09/2018 |
Open Two Way Traffic |
Monday |
24/09/2018 |
Open Two Way Traffic (during day) One way (outside peak hours) |