Date: 30 Jun 2025
Lifford-Stranorlar Members visit Ballybofey Social Housing Construction

The Elected Members of the Lifford-Stranorlar Municipal District visited the new social housing homes under construction at Coill an Airgid, Ballybofey, on 27th June 2025.
The development consists of 14 no. energy efficient social housing units which will be delivered over three phases by MBC Building Contractors Ltd.
- Phase 1 – consists of 3 units (3 x 2 bed single-storey dwellings) due to be completed by the end of June 2025.
- Phase 2 – consists of 4 units (2 x 3 bed two-storey dwellings and 2 x 2 bed apartments) will be completed by September 2025.
- Phase 3 – consists of 7 units (2 x 2 bed two-storey, 3 x 3 bed two-storey, 2 x 2 bed apartments) will be completed by the end of 2025.